Work planned Monday to Friday.

Deck construction work on the Tappan Zee Bridge will continue April 22 through April 26, according to the the New York State Thruway Authority.

The work schedule, however, can be changed in case of inclement weather. 

Monday, April 22 through Friday, April 26

Find out what's happening in Nyack-Piermontwith free, real-time updates from Patch.

During the daytime hours, the contractor will be working within designated maintenance lane closures and/or underneath the bridge.

Nighttime lane closures set for Monday, April 22 through Friday, April 26 

Find out what's happening in Nyack-Piermontwith free, real-time updates from Patch.

Monday, April 22 and Tuesday, April 23

Work will begin at 8 p.m. resulting in the closure of one left southbound lane and an additional left southbound lane at 10:30 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of two left northbound lanes at 9 p.m. and an additional left northbound lane at 10:30 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m. 

During Monday and Tuesday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 8 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Monday and Tuesday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Wednesday, April 24

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 10:30 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of one left northbound lane at 9 p.m. and an additional left northbound lane at 11 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Wednesday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 8 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Wednesday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Thursday, April 25

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 11 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of one left northbound lane at 9 p.m. and an additional left northbound lane at 11:30 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Thursday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 8 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Thursday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Friday, April 26

Work will begin at 9 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 12 midnight until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of one left northbound lane at 10 p.m. and an additional left northbound lane at 12 midnight until 6 a.m., also on theTappan Zee Bridge. At least one lane southbound and one lane northbound will be opened to traffic from 9 p.m. to 6 a.m.

During Friday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 9 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack). 

During Friday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 10 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Saturday, April 27 and Sunday, April 28

No work scheduled.

The nighttime lane closures on Monday through Friday are required in order for the contractor to continue with miscellaneous work on the Tappan Zee Bridge.  